Old Town Plaza Improvements

Old Town Plaza Construction Tape

Project Overview

Old Town Plaza improvements will be constructed over 3 phases. Phase 1 was completed Summer 2017.

In October 2018, the old masonry wall was removed and replaced with chain link fence.  The section of the masonry wall was pressure washed and painted.  Work included the installation of planters, new irrigation service, bollards and signs. 

Phase 2 design will begin January 2019 with construction anticipated for Winter 2019.  The work includes construction of a landscape plaza with curved trellis and seating at Elk Grove Boulevard and Railroad Street. 

Phase 3 schedule and funding is to be determined.

Phase 2 and 3 Contact Information
For additional comments, questions or concerns, contact:

E-mail:  scarlson@elkgrovecity.org
Mail: City of Elk Grove, Public Works Department
Stephany Carlson, Project Manager
8401 Laguna Palms Way
Elk Grove, CA 95758
Phone: 916.478.2212




 Old Town Plaza Phase 1    Phase 2  
Phase 3
Phase 1    Phase 2   Phase 3 

Railroad Street and Grove Street improvements

Design for Railroad Street and Grove Street improvements started July 2018.  Improvements will include, street reconstruction, sidewalks, curb & gutter, ramps, utilities, drainage improvements, street lighting, and construction of two parking lots.  Construction is anticipated to begin in late summer or fall of 2019. 

Conceptual Plan

Railroad Street and Grove Street improvements Contact Information
For additional comments, questions or concerns, contact:

E-mail:  kparsons@elkgrovecity.org
Mail: City of Elk Grove, Public Works Department
Kristin Parsons, Senior Civil Engineer
8401 Laguna Palms Way
Elk Grove, CA 95758
Phone: 916.478.2236

 