COVID-19 We're open, but City Hall building access is controlled. A face covering is required. Try us online first! COVID-19 Updates

Old Town Plaza Improvements

Project Overview

The Project will result in the construction of a public plaza with a large open air pavilion, public restroom, a variety of outdoor public seating and trellis structures with walkways, landscaping, lighting, and bike parking. The goal of the Project is to create a formal public gathering space to accommodate existing events, expand opportunities for future events, and establish a community gathering space centrally located within Old Town Elk Grove. The Old Town Plaza is located at 9615 Railroad Street at the corner of Elk Grove Boulevard and Railroad Street.


Current Status

The construction contract for the Railroad Street Improvements (WTR049) and the Old Town Plaza Phase 2 and 3 (WCE022) Projects was awarded to Western Engineering Contractors, Inc. by Council at their May 13, 2020 meeting.  Construction is anticipated to begin this summer and is anticipated to be completed in the Spring of 2021.

Photo Gallery

Select a photo to view it larger

09/17/20

09/17/20

09/17/20

08/19/20

08/19/20

08/19/20

07/21/20

07/21/20

07/17/20

07/17/20

07/17/20

06/17/20

06/17/20


Funding

The project is funded by Drainage Fee, Senate Bill 1 Local Street and Roads (SB 1 LSR), and General Fund Capital Reserve.

 


 

Schedule 

Date Description
October 2012 City of Elk Grove purchased the property from Union Pacific Railroad.
July 11, 2013 City partnered with Sacramento Area Council of Governments (SACOG) and the Urban Sustainability Accelerator at Portland State University to consider land use constraints and opportunities for the Project site.
Fall 2013 Citywide survey was conducted requesting input on the desired use of the Project site. The survey concluded that “residents view Old Town Elk Grove as a destination for special events”.
March 26, 2014 The survey results were presented to City Council at their March 26, 2014 meeting.
February – April 2015 Staff interviewed 15 stakeholders representing member of community organizations adjacent property and business owners, and developers. Participating community organizations included members of the Trails Committee, Old Town Foundation, Chamber of Commerce, and the Historic Preservation Committee.
June 24, 2015 City Council considered the community input and directed staff to move forward with the Project and conduct additional public outreach to explore design options
September 2, 2015 The City hosted a pop-up workshop at the project site concurrent with Food Truck Mania to receive community preferences for public space development types and uses on the property. There were three conceptual design options and were asked to select their preference. The results of these selections were shared with Council December 2015.
December 9, 2015 Council received an update on the Old Town Plaza and authorized staff to proceed with design. 
December 15, 2016 City Planning Commission recommended the City Council approve the proposed land use change and design review for the Project
January 7, 2017 City Council adopted the Initial Study/Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program; adopted the proposed general plan amendment and approved the Capital Improvement Program design review for the Project (Council Resolution 2017-009).
Environmental Documents
Summer 2017 The first phase of the project was completed resulting in a public restroom facility and other minor site improvements.
May 14, 2019 A joint public outreach meeting was held at the Elk Grove Unified School District Board Room.
May 30, 2019 Disability Advisory Committee (DAC) meeting presentation.
July 18, 2019 Art Commission meeting presentation.
December 2019 Design Completed 
 January 15, 2020  Advertise to receive bids
 February 27, 2020  Bid Due Date
 March 11, 2020 City Council rejected all bids and re-bid the Projects
 March 18, 2020  Re-advertise to receive bids
 April 9, 2020  Bid Due Date
 May 13, 2020  Council awarded the Construction Contract
 May 14, 2020  Art Commission Meeting - Reviewed and discussed art selection panel recommendations
 Summer 2020  Art Commission - Proposed art to be reviewed and selected by the Art Commission
 Summer/Fall 2020  Present art piece(s) for the Project site to Council as recommended by the Art Commission
 Summer 2020  Begin Construction
 Spring 2021  Construction Substantially Complete
 Spring 2022  Plant Establishment Period Complete

Contact

For comments, questions or concerns, contact:

E-mail: scarlson@elkgrovecity.org

Mail: City of Elk Grove, Public Works Department
Stephany Carlson, Project Manager
8401 Laguna Palms Way
Elk Grove, CA 95758

Phone: (916) 478-2212