Arterial Road Rehabilitation

Project Purpose and Overview

The purpose of this project is to rehabilitate or repave portions of Waterman Road and Elk Grove Florin Road while also adding class II (on-street) bike lanes. The City will design and construct a mid-block pedestrian crossing along Elk Grove-Florin Road north of Valley Oak Lane. Future connectivity will be made possible along Waterman Road for the City's bike lane network, while reducing annual pavement maintenance costs and extending the life of the road pavement for improve ride quality. Segment 9 on Elk Grove Boulevard is delayed due to right-of-way complexities and will be constructed at a later time.


Current Status

Environmental process was completed in January 2021 with the issuance of the NEPA Categorical Exclusion. Current critical tasks are to finalize the Plans, Specifications and Estimate, and to coordinate relocation of the existing utilities with the utility providers.


Exhibits

View Map

View Map Larger


Funding

Source Amount
SB1 Streets and Roads $790,000
Measure A Maintenance $2,296,833
Federal Grant #1 $2,000,000
Elk Grove Roadway Fee $275,000
Federal Grant #2 $845,697
Drainage Fee $1,040,000
Total $7,247,530

Public Outreach


Environmental Document

City Council adopted the CEQA Initial Study and Mitigated Negative Declaration on September 23, 2020. Caltrans issued the NEPA Categorical Exclusion on January 20, 2021.


Project Schedule

Date Description
October 2018 Project was presented to Trails Committee and Open House conducted
April 2021 Complete Final Design
July-September 2021 Utility Relocations
January 2022 Advertise Project for Construction
March 2022 Award Construction Contract
Summer - Fall 2022 Construct Improvements