Elk Grove Florin Road and Elk Grove Park Sidewalk Infill

Project Purpose and Overview

This is a joint project between City of Elk Grove and Elk Grove Unified School District (EGUSD). The City will design and construct new sidewalk along the east side of Elk Grove Florin Road from Castle Park Drive to south of Parkside Drive. This also includes added or enhanced pedestrian crossings of Elk Grove Florin Road to connect to the existing path system within Elk Grove Park. A new flashing crossing light will be installed at Lismore Drive. After completion of construction, EGUSD will implement a 2-year program to encourage pedestrian and bicycle use of the new improvements.


Project Status

The City has completed design of the project and relocation of existing power poles is starting during November 2020. Elk Grove Water Service has completed relocation of their facilities. All right of way acquisitions have been completed. The City has requested allocation of construction funds from the California Transportation Commission at the December 2-3, 2020 meeting. The City will bid the project during December 2020 to January 2021 and award the construction contract in February 2021. Utility relocations will continue until start of the sidewalk construction in March-April 2021 dependent on weather.


Exhibit

Note: Final Design varies slightly from the following Exhibits.

Exhibit 1

View Exhibit 1

Exhibit 1

View Exhibit 2


Funding

The project work is funded by a Cycle 3 Active Transportation Program (ATP) Grant using SB1 funds as well as local funds. The ATP grant funds were used for the Project Approval and Environmental Document phase (CEQA). ATP grant funds will also be used for the Construction and follow-up 2-year EGUSD program, to encourage more pedestrian and bicyclist use.

Project Funding Source
Gas Tax $245,680
SB1-ATP Grant $814,000
LTF-Bike/Ped $497,500
Drainage Fee $780,020
Measure A Safety, Streetscaping, Pedestrian and Bicycle Facilities (SSPBF)  $569,500
Total $2,906,700

Public Outreach

To join our virtual Zoom meeting on September 22, 2020 at 11 a.m., please pre-register by clicking below on the Elk Grove Florin Road and Park Way Crosswalk Relocation Meeting Registration link.


Environmental Document


Project Schedule

Date Description
May 2018 Complete Final Design
October 2018 Project was presented to the Disability Advisory Committee for feedback
Fall 2020 Begin Utility Relocation
Winter 2021 Advertise Project for Construction
Spring-Summer 2021 Begin Construction for Improvements
Fall 2021 Construction for Improvements Complete
School Year 2021 & 2022 EGUSD non-infrastructure effort to encourage non-motorized methods of school commuting.