Laguna Creek and Whitehouse Creek Multi-Functional Corridor Project

Laguna Creek and Whitehouse Creek Multi-Functional Corridor Project

Laguna Creek Inter-Regional Trail Crossing at State Route 99

Project Purpose and Overview

This project will provide a maintenance/access facility to Laguna Creek to perform maintenance activities within the Creek and enhance the City bicycle and pedestrian transit system. 

The multi-modal trail project will connect on the west with The Laguna Creek Inter-Regional Trail Crossing at State Route 99 Project (WTL016), which is currently in the Project Approval and Engineering Document Phase of design, to the Camden Park Neighborhood on the East.

Current Status

The City completed 35% design in April 2023, and the environmental document (Mitigated Negative Determination) was adopted by City Council on July 26, 2023.  Final Design is expected to begin by Fall 2023.

Funding Summary

The project work is funded by local drainage funds

Project Funding Source:

Drainage Fee - $5,954,900

Project Total = $5,954,900

Left Content

Date

September 2023

December 2023

Winter 2024

Spring 2025

Summer 2025

Right Content

Description

Notice to Proceed with Final Design

Begin Environmental Permitting

Complete 95% Plans

Complete Final Plans and Bid

Begin Construction