Laguna Creek Inter-Regional Trail Crossing at State Route 99
Project Purpose and Overview
This project will provide a maintenance/access facility to Laguna Creek to perform maintenance activities within the Creek and enhance the City bicycle and pedestrian transit system.
The multi-modal trail project will connect on the west with The Laguna Creek Inter-Regional Trail Crossing at State Route 99 Project (WTL016), which is currently in the Project Approval and Engineering Document Phase of design, to the Camden Park Neighborhood on the East.
Current Status
The City completed 35% design in April 2023, and the environmental document (Mitigated Negative Determination) was adopted by City Council on July 26, 2023. Final Design is expected to begin by Fall 2023.
Funding Summary
The project work is funded by local drainage funds
Project Funding Source:
Drainage Fee - $5,954,900
Project Total = $5,954,900
Date
September 2023
December 2023
Winter 2024
Spring 2025
Summer 2025
Description
Notice to Proceed with Final Design
Begin Environmental Permitting
Complete 95% Plans
Complete Final Plans and Bid
Begin Construction